Guide · Grid services

Grid-Forming vs Grid-Following Inverters in BESS

Grid-forming (GFM) inverters act as a controlled voltage source: they set their own voltage and frequency reference, so they can black-start a dead network, hold an island, and provide synthetic inertia. Grid-following (GFL) inverters act as a current source, using a phase-locked loop (PLL) to sync to an existing grid voltage and inject power in step with it, so they cannot start or stabilise a grid on their own. The sharpest contrast appears in a fault: a GFM saturates its current at a hardware limit while holding voltage, whereas a GFL rides through or trips.

At a glance

DimensionGrid-following (GFL)Grid-forming (GFM)
Source type Current sourceVoltage source (behind impedance)
Sets V and frequency No — follows grid via PLLYes — holds its own reference
Synthetic inertia / RoCoF Fast response, after PLL delayInherent, near-instant
Black-start capability NoYes
During a grid fault Rides through or tripsSaturates current at limit, holds V
When required Default IBR interconnect (IEEE 2800-2022)Weak grids — GB GC0137, AEMO NEM

GFM vs GFL at a glance. Requirements are still evolving — always cite the specific grid-code edition and year.

Voltage source or current source: the defining difference

A grid-following inverter is a current source. It measures the grid voltage waveform with a phase-locked loop (PLL) and injects current at a commanded magnitude and phase relative to that reference. It needs a stable voltage to lock onto — remove the grid and it has nothing to follow. Almost all utility-scale solar and storage inverters deployed to date are GFL.

A grid-forming inverter is a voltage source behind a coupling impedance. It holds an internal voltage magnitude and phase (frequency) reference and lets current flow as the network demands, much as a synchronous generator does. Because it defines the waveform rather than chasing it, a GFM can establish voltage on a dead network, run an island, and share load with other sources.

The practical rule: a GFL asks 'what is the grid doing, and how much current should I inject?'; a GFM asserts 'this is what the voltage and frequency will be, and I will hold them.'

How a grid-forming inverter sets frequency and voltage: droop

A GFM does not hold one rigid frequency — it droops. Its frequency reference falls slightly as it exports more active power (f–P droop), and its voltage reference falls as it supplies more reactive power (V–Q droop). A dead-band keeps it from reacting to trivial deviations, and the slope sets how aggressively it shares load.

Droop is what lets many voltage sources run in parallel without fighting. Because each unit lowers its frequency the same way under load, they share power in proportion to their droop slopes — the identical mechanism that let synchronous machines parallel for a century. As synchronous generation retires, GFM BESS supplies the reference the grid once took from spinning machines. The droop visual shows the operating point sliding along the f–P and V–Q curves as dispatch changes.

f-P / V-Q
speed
P setpoint0.21pu
Frequency59.901Hz
Q setpoint0.24pu
Voltage ref.0.989pu
Frequency droopf-P
Voltage droopV-Q
Control visualization - adjust dispatch and slopes to see the operating point move across f-P and V-Q droop curves.

Synthetic inertia and RoCoF

Neither inverter type has spinning mass, so neither provides true mechanical inertia. But after a sudden generation loss they behave very differently. On a low-inertia system, frequency falls fast — a steep rate of change of frequency (RoCoF) toward a deep nadir that can trigger under-frequency load shedding (UFLS).

A GFM responds to a frequency deviation inherently and within milliseconds, because its power output follows directly from the angle across its coupling impedance — there is no measurement loop in the path. This synthetic (or virtual) inertia flattens the initial RoCoF and lifts the nadir. A GFL can also deliver fast frequency response, but only after its PLL and control loop detect the deviation, adding delay. Neither replaces mechanical inertia; GFM emulates it most closely. The RoCoF visual shows how inertia and fast response together decide whether frequency recovers before the UFLS threshold.

H / RoCoF / UFLS
Higher inertia slows RoCoF. Larger lost generation/load deepens the nadir.
RoCoF-0.50Hz/s
Frequency nadir49.48Hz
Time to nadir2.8s
Quasi-steady49.75Hz
Frequency response after generation lossH / RoCoF / UFLS
nominal 50.0 Hzquasi-steadyUFLS 49.0 Hzinitial RoCoF0510152025303540time after generation loss (seconds)system frequency (Hz)48.8
t = 0.0 sf = 50.00 HzH = 5.0 sloss = 10%
speed
H is aggregate system inertia on the system power base. Higher H flattens the initial slope and raises the nadir while primary response and AGC catch up.
Control visualization - autoplay the generation-loss event, scrub the timeline, or adjust inertia and lost generation to see RoCoF and nadir move.

Behaviour during a grid fault: current saturation vs trip

This is where the two architectures diverge most. A GFL inverter controls current directly, so during a voltage sag it can be commanded to reduce current or inject reactive current, then either ride through per the grid code or trip on its protection thresholds. Its current is inherently bounded because current is the quantity it regulates.

A GFM holds voltage, so in a fault it tries to source whatever current that voltage demands across the now very low fault impedance. That request can far exceed the converter rating, so the PCS hard-limits — saturates — the current at roughly 1.1–1.2 pu of rated. Counterintuitively, a strong, low-impedance grid saturates a GFM sooner than a weak one, because I = ΔV/Z and Z is tiny. This current headroom is the single biggest hardware constraint on GFM, and the reason a converter cannot mimic the large fault infeed of a synchronous machine. The saturation visual animates the strong-grid current request clipping before the voltage reference is reached.

I = dV / Z
strong grid I req.1.50pu
strong grid I out1.00pu
weak grid I out0.12pu
V error0.010pu
Current demand and limitI = dV / Z
Voltage trackingV response
speed
strong-grid output 1.020 pu, weak-grid output 1.030 pu, reference 1.030 pu
Control visualization - change the current limit and watch strong-grid tracking clip before the voltage reference is reached.

Black-start capability

Only a voltage source can energise a dead network, so black start is a GFM-only capability. Starting from zero volts, a GFM raises voltage and frequency on a soft V/f ramp, energises transformers and cables, and picks up load blocks one at a time.

The constraint, again, is current. Close a breaker into a transformer at full voltage and the core saturates past its roughly 1.15 pu flux knee, demanding 5–10x rated magnetising inrush — current a converter limited to about 1.2–2.0 pu cannot supply, so it distorts its voltage or trips. The soft ramp raises volt-seconds slowly so core flux never crosses the knee and the inrush is never demanded in the first place. Each load block must fit the headroom between served load and the current limit, or the island collapses. The black-start visual traces bus voltage, delivered versus demanded current, and core flux as blocks are picked up.

GFM / BLACK START

When is each required? IEEE 2800, GC0137, AEMO

For most interconnections today, GFL remains the default and is sufficient on a strong grid. IEEE 2800-2022, the US standard for interconnecting inverter-based resources to transmission systems, sets ride-through and frequency/voltage support requirements that GFL can meet; it specifies capabilities rather than mandating grid-forming outright.

Grid-forming is increasingly required where inverters dominate and system strength is low. In Great Britain, National Grid ESO's Grid Code modification GC0137 introduced a Grid Forming specification for new connections. In Australia, AEMO has published grid-forming specifications and guidance and is driving GFM through connection conditions in weak parts of the NEM, with several large storage projects procured specifically for grid-forming capability. The direction of travel is consistent: as synchronous plant retires, more of the fleet must form the grid rather than follow it. Always cite the specific edition and year — requirements are still evolving.

Frequently asked

What is the difference between grid-forming and grid-following inverters?
A grid-following (GFL) inverter is a current source: it uses a phase-locked loop to measure an existing grid voltage and injects current in sync with it, so it needs a live grid to operate. A grid-forming (GFM) inverter is a voltage source: it sets its own voltage and frequency reference, so it can establish and stabilise a grid, including black start and islanded operation.
Can a grid-following inverter perform a black start?
No. Black start means energising a dead network from zero volts, which only a voltage source can do. A GFL inverter has to lock onto an existing voltage before it can inject current, so it has nothing to follow on a de-energised grid. Black start is a grid-forming capability.
Is grid-forming better than grid-following?
Not universally. GFM is more capable — it provides voltage and frequency reference, synthetic inertia, and black start — but it is constrained by converter current headroom (roughly 1.1–1.2 pu) and needs careful control tuning, especially on strong grids. On a strong grid with ample synchronous support, GFL is simpler and fully adequate. The right choice depends on system strength and grid-code requirements.
Why does a grid-forming inverter saturate current in a strong grid?
Because the current needed to correct a voltage error follows I = ΔV/Z, where Z is the coupling impedance. A strong grid has very low impedance, so even a small voltage step demands current well beyond the converter's roughly 1.1–1.2 pu limit, forcing it to clip. A weaker, higher-impedance grid asks for far less current for the same step, so it saturates later.
Do grid codes require grid-forming inverters?
Increasingly, in low-system-strength regions. Great Britain's Grid Code modification GC0137 introduced a Grid Forming specification, and AEMO in Australia mandates grid-forming behaviour through connection conditions in weak parts of the NEM. IEEE 2800-2022 in the US specifies inverter capabilities (ride-through, frequency and voltage support) rather than mandating grid-forming outright. Always check the specific edition and jurisdiction.

References

Standards and authoritative sources behind this guide:

  1. IEEE 2800-2022 — IEEE Standard for Interconnection and Interoperability of Inverter-Based Resources (IBRs) Interconnecting with Associated Transmission Electric Power Systems — IEEE , 2022
  2. Grid Forming Technology: Bulk Power System Reliability Considerations (Reliability Guideline) — NERC , 2021
  3. Research Roadmap on Grid-Forming Inverters (NREL/TP-5D00-73476) — NREL , 2020
  4. IEEE 1547-2018 — IEEE Standard for Interconnection and Interoperability of Distributed Energy Resources with Associated Electric Power Systems Interfaces (frequency-droop and volt-var/dead-band response) — IEEE , 2018
  5. IEEE Std 2800-2022 — IEEE Standard for Interconnection and Interoperability of Inverter-Based Resources (IBRs) Interconnecting with Associated Transmission Electric Power Systems (frequency response, RoCoF ride-through, and fast frequency response requirements) — IEEE , 2022
  6. Fast Frequency Response Concepts and Bulk Power System Reliability Needs — NERC (North American Electric Reliability Corporation), Inverter-Based Resource Performance Task Force , 2020
  7. Inertia and the Power Grid: A Guide Without the Spin (NREL/TP-6A20-73856) — NREL (National Renewable Energy Laboratory), US DOE , 2020
  8. Rate of Change of Frequency (RoCoF) withstand capability — ENTSO-E guidance note for the network code on requirements for grid connection — ENTSO-E (European Network of Transmission System Operators for Electricity) , 2018
  9. IEEE Std 2800-2022 — IEEE Standard for Interconnection and Interoperability of Inverter-Based Resources (IBRs) Interconnecting with Associated Transmission Electric Power Systems (current-limiting, ride-through, and reactive current injection requirements) — IEEE , 2022
  10. Grid Forming Technology: Bulk Power System Reliability Considerations (White Paper — grid-forming inverter current limiting and response during grid disturbances) — NERC (North American Electric Reliability Corporation) , 2021