Philippines PV (PGC 2016 Fig 4.4) — ride-through requirements

The LVRT envelope a grid-scale battery must meet under Philippines PV (PGC 2016 Fig 4.4) (Philippines), digitized breakpoint by breakpoint and checked against the clause it came from.

Part of: the grid-code ride-through chart — compare this against 63 other standards in 42 countries.

What this is, and is not. A reading aid compiled from the clause cited below — not a compliance document. The primary text governs. Every value here was read from a current primary source.

Breakpoints

Times are seconds from the start of the disturbance. Voltage is per-unit of nominal; frequency in hertz. An LVRT curve is a lower boundary (stay connected while voltage is on or above it), an HVRT curve an upper boundary, and FRT gives the band between its High and Low boundaries.

Event Duty Breakpoints Status
low-voltage ride-through (LVRT) ride-through 0.001s → 0 pu; 0.15s → 0 pu; 0.151s → 0.3 pu; 0.6s → 0.3 pu; 0.601s → 0.38 pu; 1.2s → 0.38 pu; 1.201s → 0.53 pu; 1.8s → 0.53 pu; 1.801s → 0.68 pu; 2.4s → 0.68 pu; 2.401s → 0.83 pu; 3s → 0.83 pu; 3.001s → 0.9 pu verified

Where these values come from

  • LVRT Philippine Grid Code, 2016 Edition (ERC Resolution No. 22, Series of 2016), GCR 4.4.4.4.1(a)-(d) and Figure 4.4 'Low voltage withstand capability – PVS'.